A digest of the main changes on Network Rail, London Underground and Northern Ireland Railways infrastructure during March 2020, compiled by Martyn Brailsford of the Branch Line Society (www.branchline.uk).
March saw a downturn in reportable work, partially due to the coronavirus pandemic. However, one significant project that has moved forward is the new platform and track at Stevenage.
ANGLIA
Southminster (2:10A)
Newmans (44M 25ch), Standford’s Farm (39M 27ch) and Tyle Hall (39M 58ch) User Worked Crossings (UWC) have all been upgraded with miniature Red/Green lights to become Overlay Miniature Stop Light (OMSL) crossings. Between Beccles and Lowestoft (2:8) Wrights User Worked Crossing (UWC) at 113M 57ch has been upgraded with miniature Red/Green lights to become an Overlay Miniature Stop Light (OMSL) crossing.